Activity Site / Block Duration

See the hours, units and cost per activity on each site and block, with a chart, saved pivot views and an exportable table

This report shows how many hours employees spent on each activity, per site and block, per day, with the units captured and the cost. Use it to see where work happened and what it cost, for example how many employees worked on each site.

Open and generate the report

  1. Select the date range.

  2. Optional: under Filter Activities, choose the activities to include. Leave it empty for all activities.

  3. Optional: under Graph Grouping, choose how the chart groups the hours: Activity, Activity Category or Employee Team.

  4. Click Generate.

You need permission to read employee clocks to open this report.

Chart

The chart shows, for each group you chose under Graph Grouping, the total hours, the number of different employees and the total cost for the date range.

Pivot views

Below the chart, a pivot table summarises the same data. Choose a view in the drop-down above it:

  • Views marked D are default views that AllWage provides.

  • Other views were added for your business.

  • Add new creates your own view: choose the rows, columns and values to group and total, for example sites as rows and the number of employees as the value.

The text next to the drop-down describes the selected view. See Custom Reports for how the editor works.

Table and export

The table at the bottom has one row per employee, activity, block and day, with these columns: Date, Activity Category, Activity, the site, Block, Area, Produce, Employee Group, Employee Name, Employee Number, Hours, Units, Calculated Units, Cost (R) and Rate/Hour (R).

  • Columns shows more columns, such as Activity Code, Block Size (Ha), Employee Label, Target Interval (H/D), Calc. Unit Target and Unit Target, or hides them.

  • Type in the search box to filter the rows.

  • Export downloads the table to Excel.

If hours or units look wrong, use Clocks data review or Activities data review at the bottom of the report to check the captured records.